The sealing team are still in the rafters .....
..... but have now moved to the final outer area.
The access pipe to the cistern has been plastered,
and the tiled mounting plate for the entrance hall loo fittings has been set.
The final pieces of replacement glass have arrived and await the removal of the scaffolding before being put in place.
Kieran's tile cleaning operation has moved to the Studio Flat.
Sabina visited the factory to observe the testing of the folding doors.
Having passed with flying colours, they have been delivered to site and await erection.
And finally, the big site clearance continues unabated.