WEEK 234 - FINISHING, FINISHING

 The race continues to complete for BFB² - 42 days to go.
 


The stair rails have been cleaned and waxed.


 


 

 
The proliferation of speakers continues - these being the pair under the seat at the top of the Tower.

 
The extractor fan over the Argor has been fitted.

The kitchen units are in the final stages of installation.

 
 
The 'double to twin' beds laid bare.  Due to their weight, a crane is required to separate them!

Loo roll holders and towel rails are beginning to appear.


 
Sabina's mosaic in the pool wet room nears completion.



 
 
 
Work has begun on the pool - the steps plastered, skimmers installed, cabling for the fibre optic lights set into the jacuzzi wall, and the top wall of the jacuzzi cast.

 
The outside pool shower is beginning to take shape.
 
 
The main entrance steps have been plastered and the side walls inserted.




 
Sabina hard at it as usual .......

 
... and looking relaxed for a change.

 
New light at the top of the Tower.

 
The Tea House beginning to look like the original computer generated images.

 
 