Week 7 has seen the continuation of formwork, steel and concrete with this being a general view showing all bar one of the columns now erect.

Some bamboo has been removed from the pump house roof ……

to form the scaffolding for the kitchen bay window form work


The floor of the tower has been caste …

and the columns and beams for the first floor are coming along well.


The first layer of the kitchen wall is complete, with the columns to be caste early next week.

The flat foundations have been caste and block work commenced in the stairwell.