Saturday, 11 February 2012

WEEK 197 -TILES & CHUTE

Another good week.


The tiles have been laid on the entrance hall veranda,


and the metal sleeve for the glass insert put in place.


Shevran has been constructing frames for the mirrors.


Sabina has continued work on the work surfaces for the kitchen.



The wooden cover for the laundry chute has been inserted into the wall outside the Master Bedroom.



The scaffolding around the Tower has been reinforced in preparation for the next coat of paint.




The new generator room is almost complete.




Some passing shots.