Sabina & Kenrick discussing the week's wages claim!
A few shots of the doors with their complete coats of sealant.
The painters are continuing to coat the internal walls and ceilings with white primer which increases the apparent size of all of the rooms.
The Tower walls have been painted (twice!) and match beautifully the colours of the wooden steps.
Sabina has been hard at work with more polished cement - here the seat ....
.. and wash basin stand in the Guest Bedroom.
The tile work in the Master Bedroom en-suite has been started, ......
........ and in the Studio Flat, the floor tiling is now complete .......
.... and has been started in the bathroom.
The scaffolding has finally been removed from the southern end of the house, ......
..... and has started to be erected around the Tower prior to plastering the outside walls.
No comments: