A good week with more progress than in recent times. Doors have been collected from the manufacturers and are being installed.
It's good to see Sextus back on site leading the painting and sealant team.
Terminus/Castro has also returned to assist in hanging the doors.
The wooden step inlays for the Tower are almost complete.
The painters have been filling/sanding/painting the internal walls of the Tower.
Sabina has been busy on the Tower bench seat.
Here, the tiling of the Gust Bedroom shower seat is in progress.
The 'loft bats' are continuing to sand and seal the sky lights.
The newly painted ridge tiles are weathering in well.
The painters have discovered hand prints of a nocturnal poltergeist indented in the wall of the Tower.
Kenrick has been suffering from 'man flu' this week .......
...... but managed to heave himself out of the van to assist Sabina holding colour cards for Brett's approval.
The scaffolding is still up awaiting a suitable cleaning agent for the tiles.