Saturday, 4 December 2010

WEEK 135 - FLOORING ON

Another good week weatherwise and, with the team back up to full strength, the project is moving forward slowly but surely.


As the lounge floorboards approach the entrance hall/kitchen, the joists are being laid/renovated.



The lounge floor is nearing completion.



The mason is re-pointing around the stone work outside the kitchen windows.

More windows and frames have been collected and are being fitted.

Kenrick and Plywood, the aptly named carpenter who is a new addition to the team.




Everyone can't wait for the scaffolding to be removed!!!!!!

The first of the internal doors have been hung.


The decorative lintels have been fashioned outside the studio flat.



The side to the kitchen stairs has been cast.