A reasonable week weather wise although strong winds and thundery showers restricted work on the roof.
The pool has eventually been emptied of water and post hurricane debris.
The Car Port ceiling has received the final coat of Filter 7.
A few more windows have been returned after adjustments and are being fitted.
The squared window-sills are now rounded.
The curved kitchen windows are now fully plastered in position ........
........ as are the Master Bedroom en-suite windows.
The external kitchen steps are now fully paved and work on the side wall started.
The mahogany arches are almost complete. Lifting them into position and fixing in place is going to be an interesting operation!
The cleaning of the south facing wall stonework is complete ......
...... with Anthony re-pointing where necessary.
The ridge tiles continue to be a challenge with only a few being put in place but as yet with no fixings. More will be fired next week.
Kenrick and O'Neil have commenced laying the lounge floor.
Brett has returned to UK, but Sabina remains on-island to chase the various sub-contractors and make finishing decisions.