WEEK 122 - WINDOW FRAMES GALORE

A week of good and bad news.  The bad concerned Kenrick and half of the Team contracting a virulent virus at the begining of the period resulting in little work being possible.  The good was that most were recovered by mid-week, the hurricanes continued to dissipate or pass to the north, and we took delivery of 21 window frames.









The masons have been completing the stone work on the external kitchen wall.



Meanwhile, Guy the electrician has been completing the pull through of the wiring and installing the conduit and cables for the sound system.




Finally, the roof tiles have been moved once more in preparation for the plastering of the guest room floors.