The plasterers have completed the outer face of the drive wall ...
.... and moved on to plaster the tops of the walls where the rafters have been cast into the block.
They then moved on to plaster the top of the wall on the Tower.
Working precariously high, the carpenters have extended the scaffolding, inserted the next piece of the ridge beam and the first 2 rafters are in place on the north roof.
Kenrick directing operations from the safety of the beam!