After a slow first week of 2009, week 37 has seen the Team accelerate to the speeds of 2008.

The first 3,000 roof tiles have been collected and stored on site - only 27,000 to go!! The colour is not truly representative because of the poor quality flash .......

this is the real thing!

All the tiles for the Studio Flat have also been delivered and unloaded manually from the top road.


Construction has started on the retaining wall for the Car Port .......

with the first beam being cast on Friday just prior to cease work.