We have just returned from 2 weeks in UK and are even more convinced that we made the right decision to move to St Lucia! Whilst away, Brett has been on-island with his Mum and the Team took a week off to recuperate. Sabina has been rushed off her feet entertaining and was thus far too busy to complete the Blog. Therefore this is a short amalgam of the work over the past 3 weeks taken with a camera very low on battery!
The finishing of the Studio Flat continues apace.
The main staircase steps have been stained.
The finishing touches have been put to the aperture above the car port.
The mahogany arches under the lounge balcony have been fitted
The scaffolding is still in place for the staining of the lintels and awaiting a final decision on further tile cleaning.
The floors have been sanded and are receiving the first coat of sealant.
Polished stone at the base of the Tower.
An unfettered Tower with the lizard almost visible.
The third and final container has arrived with loos etc and a more comprehensive edition will appear next week.